Completion certificates and retention: billing projects by progress

FundamentalsBy the alFatora team3 min readUpdated:

Contractors and service companies do not deliver bags or boxes; they deliver progress. They bill when a stage is done (30%, then 60%), and the client usually holds back part of each payment, often 10%, until the work is handed over. Tracking those held amounts in a spreadsheet is how money gets forgotten.

The case

A fit-out contractor signs a SAR 210,000 contract with a private school: interior works at SAR 150,000 and electrical works at SAR 60,000. The client holds 10% retention. The first stage, 30% of both, is done.

SAR
30% of 210,00063,000
VAT 15%9,450
Invoice total72,450
Retention held (10% of 63,000)−6,300
Due now66,150

In alFatora, step by step

  1. Create a sales order with the two contract lines, press Add retention and enter 10%, then confirm the order.
  2. Press Create delivery note and choose By percentage done. Enter 30% for every line at once, or a different percentage per line. The document is titled completion certificate.
A completion certificate form by percentage done: 30% for every line at this stage.
The completion certificate: this stage’s percentage for every line at once.
  1. Confirm the certificate, press Create invoice and issue it. The invoice keeps its full value and VAT; the retention only reduces what is due now, and it is shown on the invoice.
  2. Repeat at each stage. The order shows the progress and the total retention held so far.
  3. At handover, open the order, press Release retention and choose which invoices it covers. The held amount becomes due.
The sales order after the first stage: 30% done and invoiced, 10% retention of SAR 6,300 held, and the Release retention link.
The order tracks progress and retention until it is released.

You can filter the delivery notes list to show completion certificates only.

What you gain

  • Every progress invoice matches a completion certificate.
  • Retention is tracked per order, so it is collected at handover, not forgotten.
  • VAT is always on the full invoice value, as it should be.

Before you start

Switch on sales orders and delivery notes once, in Sales settings, the last entry of the Sell menu.

Frequently asked questions

Is retention taken off the invoice value before VAT?

No. The invoice keeps its full value and VAT; retention only reduces what is due now.

When is the held amount paid?

When you release it from the order, choosing which invoices the release covers.

Was this useful? Review alFatora on Google.

Zakat, Tax and Customs AuthorityFatooraCompatible with ZATCA Phase 2
e-invoicing requirements
Create your account